Adding and syncing items to project planIn aqua project plans are able to update automatically. This means, you can add aqua elements and synchronize them. When the element is set to specific status, e.g. closed, it will be set to finished in the project plan. In order to add a aqua element to a project plan, click the
![]() If the element's status should be set to finished automatically on a specific status, you can configure this by right-clicking it and select 'Edit'.
![]() Now switch to tab 'Synchronization'. Here you can choose, which status defines completion of the element.
![]() ![]() The element will now be updated automatically on the selected status.
|